<key-projects>
  <projects>
    <title>Acquisition Tracking System (1)</title>
    <description>This system will be used to track requisitions that have been submitted from the FDA Centers/Offices and Programs to OAGS and will provide OAGS management with a tool for tracking workload and contract actions status and running automated reports; and will allow the customer to log into the system to track the status of their requisition(s).</description>
    <dictionary></dictionary>
    <outcome></outcome>
    <accomplishment></accomplishment>
    <table>
      <title></title>
      <overall-status>
        <briefing>DELAYED</briefing>
        <prior-briefing>DELAYED</prior-briefing>
      </overall-status>
      <row>
        <type></type>
        <milestone-description>A. Award a contract for a contractor to build a web-based, stand-alone acquisition tracking system (ATS) utilizing the basic requirements, features, and functionalities of the prototype.</milestone-description>
        <milestone-date>7/1/2011</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>7/2/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>B. Develop System Requirement Specification (SRS)</milestone-description>
        <milestone-date>7/18/2011</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>7/18/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>C. Develop System Design Document (SDD)</milestone-description>
        <milestone-date>7/22/2011</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>7/22/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>D. Develop User Acceptance Testing (UAT)</milestone-description>
        <milestone-date>7/26/2011</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>7/26/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>E. Develop Version Description Document (VDD)</milestone-description>
        <milestone-date>8/1/2011</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>8/1/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>F. Conduct User Acceptance Testing (UAT)</milestone-description>
        <milestone-date>8/31/2011</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>8/31/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>G. Train OAGS staff and 2 FDA Centers on ATS (2)</milestone-description>
        <milestone-date>9/1/2011</milestone-date>
        <milestone-status>Delayed</milestone-status>
        <milestone-completion-date></milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>H. Finalize communication plan</milestone-description>
        <milestone-date>9/15/2011</milestone-date>
        <milestone-date>&lt;i&gt;(TBD)&lt;/i&gt;</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>10/3/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>I. Implement communication plan</milestone-description>
        <milestone-date>9/15/2011</milestone-date>
        <milestone-date>&lt;i&gt;(TBD)&lt;/i&gt;</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>10/3/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>J. Complete testing in Pre-production Environment</milestone-description>
        <milestone-date>10/31/2011</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>11/16/2011</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>K. Complete ATS Phased roll-out to Agency</milestone-description>
        <milestone-date>1/1/2012</milestone-date>
        <milestone-date>&lt;i&gt;(9/1/2014)&lt;/i&gt;</milestone-date>
        <milestone-status>Delayed</milestone-status>
        <milestone-completion-date></milestone-completion-date>
      </row>
      <row>
        <type>sub</type>
        <milestone-description>1. Phase One: Complete pilot within OAGS (3)</milestone-description>
        <milestone-date>10/31/2011</milestone-date>
        <milestone-date>&lt;i&gt;(10/1/2013)&lt;/i&gt;</milestone-date>
        <milestone-status>Delayed</milestone-status>
        <milestone-completion-date></milestone-completion-date>
      </row>
      <row>
        <type>sub</type>
        <milestone-description>2. Phase Two: Complete ATS roll-out to two FDA Centers</milestone-description>
        <milestone-date>11/1/2011</milestone-date>
        <milestone-date>&lt;i&gt;(12/1/2013)&lt;/i&gt;</milestone-date>
        <milestone-status>Delayed</milestone-status>
        <milestone-completion-date></milestone-completion-date>
      </row>
      <row>
        <type>sub</type>
        <milestone-description>3. Phase Three: Complete ATS roll-out to two additional FDA Centers</milestone-description>
        <milestone-date>11/1/2011</milestone-date>
        <milestone-date>&lt;i&gt;(6/1/2014)&lt;/i&gt;</milestone-date>
        <milestone-status>Delayed</milestone-status>
        <milestone-completion-date></milestone-completion-date>
      </row>
      <row>
        <type>sub</type>
        <milestone-description>4. Phase Four: Complete ATS roll-out to remaining FDA Centers/Offices</milestone-description>
        <milestone-date>1/1/2012</milestone-date>
        <milestone-date>&lt;i&gt;(9/1/2014)&lt;/i&gt;</milestone-date>
        <milestone-status>Delayed</milestone-status>
        <milestone-completion-date></milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>L. Complete 3-month defect evaluation</milestone-description>
        <milestone-date>4/1/2012</milestone-date>
        <milestone-status>Completed</milestone-status>
        <milestone-completion-date>4/1/2012</milestone-completion-date>
      </row>
      <row>
        <type></type>
        <milestone-description>M. Complete 6-month defect evaluation</milestone-description>
        <milestone-date>7/1/2012</milestone-date>
        <milestone-status>Not Yet Started</milestone-status>
        <milestone-completion-date></milestone-completion-date>
      </row>
      <footnotes>
        <note>(1) The dates in italics under the milestone due dates are modified milestone due dates which had to be updated due to real-time delays.  The milestone status reflects the revised dates.</note>
        <note>(2) OAGS Staff Training was completed on 10/20/2011; functionality to train Centers has not yet been turned on.</note>
        <note>(3) Pilot within OAGS is ongoing.</note>
      </footnotes>
    </table>
  </projects>
  <glossary></glossary>
  <related-links>
    <link>
      <url>http://www.fda.gov/AboutFDA/Transparency/track/ucm206310.htm</url>
      <text>FDA-TRACK Office of Operations Dashboard</text>
    </link>
  </related-links>
</key-projects>਍††਍਍਍਍਍਍਍