Chemical Evaluation and Risk Estimation System (CERES)
Description: Initiate development of a chemical evaluation and risk estimation system for pre- and post-market review of food ingredients. The system will enable FDA to fully leverage available data through modern computational and predictive methods for pre-market review as well as post-market monitoring of food ingredients and packaging materials.
Briefing Status: ON TRACK
Prior Briefing Status: ON TRACK
| Milestone Description | Milestone Date | Milestone Status | Milestone Completion Date |
|---|---|---|---|
|
A. Develop Structure Editor |
1/31/2010 (3/31/2011) (6/15/2011) |
Completed | 5/27/2011 |
|
B. Establish list of requirements for CERES |
3/30/2010 |
Completed | 2/26/2010 |
|
C. Gentox computational tox models |
3/30/2010 |
Completed | 3/30/2010 |
|
D. Develop high level architecture |
6/20/2010 |
Completed | 6/20/2010 |
|
E. Carcinogenicity Model developed |
7/31/2010 |
Completed | 6/30/2010 |
|
F. System Requirements external review completed |
8/31/2010 |
Completed | 8/1/2010 |
|
G. ToxML and PAFA data migrated |
9/30/2010 |
Completed | 10/25/2010 |
|
H. Chromosome Aberration Model developed and in testing |
9/30/2010 |
Completed | 10/25/2010 |
|
I. Carcinogenicity and Chromosome Aberration Model Validated |
11/30/2010 |
Completed | 12/23/2010 |
|
J. Stand up initial operational version of CERES |
12/31/2010 |
Completed | 12/23/2010 |
|
K. Completed initial testing |
2/28/2011 |
Completed | 2/25/2011 |
|
L. Apply models to all authorized food chemicals |
3/31/2011 (9/30/2011) (1/31/2013) |
On Track | |
|
M. Start operational testing |
4/1/2011 |
Completed | 3/15/2011 |
|
N. Model validation of repro-dev models scheduled for completion |
7/31/2011 |
Completed | 6/15/2011 |
|
O. End operational testing |
3/31/2012 (9/30/2012) |
Completed | 9/30/2012 |
|
P. Release of CERES Version 1, which is not a fully automated version |
3/31/2012 (9/30/2012) |
Completed | 9/30/2012 |
|
Q. Release of CERES Version 2, which is a fully automated risk assessment tool |
3/31/2013 (1/31/2014) (8/30/2013) |
Not Yet Started | |
|
R. Complete Enterprise Performance Life Cycle testing |
1/31/2014 |
Not Yet Started | |
|
S. Receive authority to operate from Chief Information Officer |
4/30/2014 |
Not Yet Started |
Footnotes
- The dates in italics under the milestone due dates are modified milestone due dates which had to be updated due to real-time delays. The milestone status reflects the revised dates.
Key Projects Legend
| Milestone Status | Definition |
|---|---|
| Not Yet Started | Work for specific milestone has not yet been started. |
| Completed | Milestone and/or overall project is completed. |
| On Track | Milestone - On track for completion by milestone deadline. Quarter status - Project is on track for completion based on overall milestone status. |
| On Hold | Milestone - On hold, but deadline for completion has not passed. Quarter status - Project is on hold, based on overall milestone status. |
| Delayed | Milestone - Delayed as it has not been completed and deadline has passed. Quarter status - Project is delayed based on overall milestone status. |
Glossary
Note: The data provided on this website is produced on an ongoing basis for performance management purposes and is subject to change due to updates of preliminary estimates, corrections, or other reasons. In addition, FDA may change the type or amount of data provided on this website at any time. Information marked as "Completed" may include measures and/or key projects for which activities are ongoing but no longer tracked as part of FDA-TRACK.