Consolidation of Life Sciences-Biodefense Complex (LSBC) to White Oak (WO) Campus

Description: Coordinate with the General Services Administration (GSA) and FDA programs and manage project activities to relocate the Center for Biologics Evaluation and Research (CBER), the Center for Drug Evaluation and Research (CDER), and the Center for Tobacco Products (CTP) to the LSBC at FDA's WO Campus in accordance with the 2009 Master Plan and schedule. The LSBC is comprised of two laboratories - Buildings 52 and 72; the expansion of the vivarium - Building 10, and two office buildings - Buildings 71 and 75. The LSBC is located on the Southeast Quadrant of the WO Campus with almost 1.2 million square feet of space to house more than 2,600 FDA employees - a large portion from CBER and CDER - who will relocate to WO from the National Institutes of Health (NIH) and other locations scattered throughout Rockville. The LSBC is intended to provide safe, certified laboratory capacity for FDA to perform its medical product responsibilities.

Information is current as of June 29, 2014.

Briefing Status: On Track

Prior Briefing Status: On Track

Milestone DescriptionMilestone DateMilestone StatusMilestone Completion Date

A. Complete substantial furniture installation for Buildings 52, 72, 10, 71, and 75 (LSBC) and common/atrium areas.

6/5/2014

Completed 6/6/2014

B. Complete punch list and change list items for furniture installations.

9/5/2014

On Track

C. Ensure adequate utilities are in place and adequately tested to ensure certification of the labs prior to occupancy : Central Utility Plant (CUP) expansion.

4/25/2014

Completed 6/29/2014

D. Ensure adequate utilities are in place and adequately tested to ensure certification of the labs prior to occupancy: Emergency Power Generation system.

5/16/2014

Completed 6/29/2014

E. Begin occupancy in stages for CBER, CDER and CTP relocating from existing locations to the LSBC.

4/25/2014

Completed 4/25/2014

F. Complete occupancy for CBER, CDER and CTP to the LSBC.

6/21/2014

Completed 6/21/2014

G. Complete laboratory occupancy for CBER, CDER and CTP to the LSBC.

8/30/2014

On Track

Footnotes

  • (1) The dates in italics are modified milestone due dates that have been updated due to real-time delays. The milestone status reflects the current reporting quarter’s status. If a milestone is missed, the milestone will remain delayed until the milestone is completed.

Key Projects Legend

Milestone StatusDefinition
Not Yet StartedWork for specific milestone has not yet been started.
CompletedMilestone and/or overall project is completed.
On TrackMilestone - On track for completion by milestone deadline. Quarter status - Project is on track for completion based on overall milestone status.
On HoldMilestone - On hold, but deadline for completion has not passed. Quarter status - Project is on hold, based on overall milestone status.
DelayedMilestone - Delayed as it has not been completed and deadline has passed. Quarter status - Project is delayed based on overall milestone status.

Glossary

Note: The data provided on this website is produced on an ongoing basis for performance management purposes and is subject to change due to updates of preliminary estimates, corrections, or other reasons. In addition, FDA may change the type or amount of data provided on this website at any time. Information marked as "Completed" may include measures and/or key projects for which activities are ongoing but no longer tracked as part of FDA-TRACK.