About FDA
Deliver PREDICT Components
Description: MARCS: Mission Accomplishment and Regulatory Compliance System, replacing failing legacy systems with reusable fail safe architecture and infrastructure to help ORA meet FDA mission.
Briefing Status: COMPLETED
Prior Briefing Status: Delayed
| Milestone Description | Milestone Date | Milestone Status | Milestone Completion Date |
|---|---|---|---|
|
1. Train & Deploy PREDICT (MARCS Imports V1.0) in all applicable Districts |
9/30/2010 |
Completed | 12/6/2011 |
|
2. Complete initial set of rules received from all Centers; deployed in PREDICT |
12/30/2011 |
Completed | 12/30/2011 |
|
3. Centers' database look-ups specs & authorization received/deployed |
12/30/2011 |
Completed | 12/30/2011 |
Key Projects Legend
| Milestone Status | Definition |
|---|---|
| Not Yet Started | Work for specific milestone has not yet been started. |
| Completed | Milestone and/or overall project is completed. |
| On Track | Milestone - On track for completion by milestone deadline. Quarter status - Project is on track for completion based on overall milestone status. |
| On Hold | Milestone - On hold, but deadline for completion has not passed. Quarter status - Project is on hold, based on overall milestone status. |
| Delayed | Milestone - Delayed as it has not been completed and deadline has passed. Quarter status - Project is delayed based on overall milestone status. |
Glossary
Note: The data provided on this website is produced on an ongoing basis for performance management purposes and is subject to change due to updates of preliminary estimates, corrections, or other reasons. In addition, FDA may change the type or amount of data provided on this website at any time. Information marked as "Completed" may include measures and/or key projects for which activities are ongoing but no longer tracked as part of FDA-TRACK.