Establish a Project Management Pilot Program in OCC (1)

Description: Assess the need and benefit of creating project manager positions in OCC to help manage resources, prioritize projects and communicate with clients about project status.

Accomplishment: OCC’s project management pilot provided a framework to implement project management within OCC. For the pilot area, accomplishments included better management of incoming requests and projects, the improved use of information technology to support the office and the development of processes that advance efficiency and effectiveness.

Milestone DescriptionMilestone DateMilestone StatusMilestone Completion Date
A. Assess need for project management in OCC 1/3/2011
Completed 1/3/2011
B. Post project management details 1/24/2011
Completed 1/24/2011
C. Select project manager detailee 3/11/2011
Completed 4/28/2011
D. Train project manager on OCC Systems 3/25/2011
(6/24/2011)
Completed 6/17/2011
E. Develop project manager performance measure to evaluate effectiveness of new position 4/15/2011
(8/15/2011)
Completed 7/1/2011
F. Prioritize duties and establish management goals for pilot program 6/10/2011
(8/31/2011)
Completed 6/24/2011
G. Complete assessment on program manager position effectiveness 7/15/2011
(9/16/2011)
Completed 11/14/2011
H. Make final decision on whether to hire project managers in OCC 8/1/2011
(9/21/2011)
Completed 11/14/2011

Foot Notes

  • (1) The dates in italics under the milestone due dates are revised milestone due dates which had to be updated due to real-time delays. The milestone status reflects the revised due dates.

Key Projects Legend

Milestone StatusDefinition
Not Yet StartedWork for specific milestone has not yet been started.
CompletedMilestone and/or overall project is completed.
On TrackMilestone - On track for completion by milestone deadline. Quarter status - Project is on track for completion based on overall milestone status.
On HoldMilestone - On hold, but deadline for completion has not passed. Quarter status - Project is on hold, based on overall milestone status.
DelayedMilestone - Delayed as it has not been completed and deadline has passed. Quarter status - Project is delayed based on overall milestone status.

Glossary

Note: The data provided on this website is produced on an ongoing basis for performance management purposes and is subject to change due to updates of preliminary estimates, corrections, or other reasons. In addition, FDA may change the type or amount of data provided on this website at any time. Information marked as "Completed" may include measures and/or key projects for which activities are ongoing but no longer tracked as part of FDA-TRACK.

-
-