Patient Network Website Development (1)
Description: Project to develop and launch the website for the new FDA Patient Network, a program that will serve as the portal for the patient advocacy community to engage with the FDA. The primary objectives of the program (and website) are to provide educational resources to the patient community, as well as facilitate engagement between the FDA and its patient stakeholders.
Briefing Status: ON HOLD
Prior Briefing Status: ON TRACK
Milestone Description | Milestone Date | Milestone Status | Milestone Completion Date |
---|---|---|---|
A. Develop project plan for research and development of website |
10/20/2010 |
Completed | 10/20/2010 |
B. Complete research to determine the needs and behaviors of patient audiences |
1/10/2011 |
Completed | 1/26/2011 |
C. Organize the site structure and content based on the results of the user research |
2/21/2011 |
Completed | 2/14/2011 |
D. Develop and have user-tested prototypes of the site |
4/4/2011 (7/31/2011) |
Completed | 7/26/2011 |
E. Select a final design for the site, including community engagement features |
6/4/2011 (8/31/2011) |
Completed | 8/21/2011 |
F. Gain internal FDA Information Technology (IT) approval to begin development |
9/30/2011 |
Completed | 10/10/2011 |
G. Set up the hardware and software infrastructure to host the site |
6/23/2011 (10/31/2011) |
Completed | 10/25/2011 |
H. Develop and populate the site with content |
9/30/2011 (1/25/2012) |
Completed | 1/20/2012 |
I. Site Launch |
10/7/2011 (2/1/2012) |
On Hold |
Foot Notes
- (1) The date in italics under the milestone due dates are revised milestone due dates which had to be updated due to real-time delays. The milestone status reflects the revised due dates.
Key Projects Legend
Milestone Status | Definition |
---|---|
Not Yet Started | Work for specific milestone has not yet been started. |
Completed | Milestone and/or overall project is completed. |
On Track | Milestone - On track for completion by milestone deadline. Quarter status - Project is on track for completion based on overall milestone status. |
On Hold | Milestone - On hold, but deadline for completion has not passed. Quarter status - Project is on hold, based on overall milestone status. |
Delayed | Milestone - Delayed as it has not been completed and deadline has passed. Quarter status - Project is delayed based on overall milestone status. |