A getinge field service engineer (fse) was dispatched to evaluate this unit, the fse began by checking the power cord and power supply and no defects were found.
Then, inspection of the contact between the cart and unit was performed and all checked ok.
The fse re-seated the unit to cart and unit was able to charge.
The battery conditions were satisfactory.
No problems were found.
The fse performed all the test per manufacture maintenance specifications.
Unit passed all functional and safety test per factory specs.
The iabp was released to the customer and cleared for clinical service.
Upon completion of our investigation, a supplemental report will be submitted.
The full name of the of the initial reporter at the event site was shortened due to field character limit.
The full name is: (b)(6).
|