Additional information: d9, h3, h4, h6, h11.H4: the lot was manufactured between october 10, 2023 - october 11, 2023.H11: the actual device and a photograph of the sample were received for evaluation.Visual inspection of the photo and actual sample did not show any abnormalities that could have contributed to the reported condition.Functional leak testing was performed, and a leak was observed between the spike port tubing and spike port connector.The reported condition was verified.The cause of the condition could not be determined; however, was most likely due to inadequate or lack of cyclohexanone being applied to the spike port connector when it was inserted into the spike port tubing during manufacturing.A nonconformance has been opened to address this issue.A batch review was conducted and there were no deviations found related to this reported condition during the manufacture of this lot.Should additional relevant information become available, a supplemental report will be submitted.
|