Additional phone number:(b)(6)
updated fields: b4, d10, g3, g6, h2, h6 (type of investigation, investigation findings, investigation conclusion), h11
corrected fields: e2, e3, g2, a1 need revert to blank, h4 need revert to balnk
a getinge field service engineer (fse) evaluated the unit and replaced the battery then performed testing.All functional and safety test were performed and passed.No fault logs were provided however a photo of the battery was attached for viewing.Based on the reported battery short run time the failure mode was confirmed.
|